Fall 2015 Sprint Schedule

posted by: Mr. Bergquist 15 November 2015 No Comment

Our Sprint Schedules (subject to modification)

—1st Monday: Sprint Planning meeting, determine Stories and Tasks
1st Thur: Initial Stand-up (Scrum) Meeting
(1st Sprint of a new project will take longer to create backlog of Stories & Tasks & Test Cases)
2nd Monday : Story Test Cases finalized & Stand up (Scrum) Meeting
2nd Thur: Stand-up (Scrum) Meeting
3rd Monday: Stand-up (Scrum) Meeting
3rd Thursday: Integration, build & testing
3rd Friday: Demonstration of new features (stories) and identification of fixes & tasks to go into next Sprint – or are we ready to release?

Schedule for 4th Sprint (about 2 Weeks): proposed…

Thur Jan 20th : Sprint Planning meeting, identify Final Milestones/Stories and Tasks.
Monday, Jan 25th: Initial Stand-up (Scrum) Meeting – check in on Tasks accomplishing Milestones/Stories for demos of functionality.
Friday, Jan 22nd: Stand up (Scrum) Meeting, discussion of what will be demonstrated and check in on Story Test Cases.
Thursday, Jan 28th: Integration, build & testing
Thursday Jan 28th – Peer Reviews (all 3) Due by end of day2015 Peer Evaluation Survey Form
Friday Jan 29th – Presentation paperwork review with Mr. Bergquist
Feb 2nd & 3rd – Final Milestone Demo’s & Presentations (20 minutes each)
Feb 4th – Final Process Reflection & Self Evaluation

Schedule for 3rd Sprint (about 2 Weeks, all January dates):

Mon 4th : Sprint Planning meeting, determine Stories and Tasks.
Thursday, 7th: Initial Stand-up (Scrum) Meeting – check in on Tasks accomplishing Stories for demos of functionality.
Tuesday, 12th : Stand up (Scrum) Meeting, discussion of what will be demonstrated and check in on Story Test Cases.
Wednesday, 13th: Early Release, short period.
Thursday, 14th: Integration, build & testing
Tuesday, 19th: Individual team Demo’s of new features (stories) and identification of fixes & tasks to go into next Sprint.  Mentors will go from team to team, not in front of entire class.

Schedule for 2nd Sprint (about 2.5 Weeks, most all December dates):

Mon 30th Nov. & Tues 1st : Sprint Planning meeting, determine Stories and Tasks.
Thursday, 3rd: Initial Stand-up (Scrum) Meeting – check in on Tasks accomplishing Stories for demos of functionality.
Thursday, 10th: Project Presentation and Expert Feedback with Amazon UX Designers
Monday, 14th : Stand up (Scrum) Meeting, discussion of what will be demonstrated and check in on Story Test Cases.
Tuesday, 15th: Start assembling code for Integration, build & testing
Thursday, 17th: Demonstration of new features (stories) and identification of fixes & tasks to go into next Sprint.
Friday, 18th: Company party.  Make any plans for work over break.

Schedule for 1st Sprint (2.5 Weeks, all November dates):

Tues 10th & Thur 12th: Sprint Planning meeting, determine Stories and Tasks (note no school 10/11 Veteran’s Day)
Thursday, 19th: Initial Stand-up (Scrum) Meeting – check in on Stories, Tasks created & Priorities (make sure you are creating Test Cases)
Tuesday,24th : Stand up (Scrum) Meeting, check in on Story Test Cases, discussion of what will be demonstrated…
Monday & Tuesday, 23rd & 24th, Integration, build & testing??
Wed, 25th: Demonstration of new features (stories) and identification of fixes & tasks to go into next Sprint -oops only about 20 minutes of class due to early release and senior meeting???

Presentation: Our Scrum Development Process (PDF)